Final Walls & Roof Complete
It has been a very exciting month to see the last of old building come down and the final walls and roof go up! The wrap around connects condos #4 and #6 and features a 8' overhang (over condo #5 west entrance, office, exercise room and guest suite). Over the next two weeks, this frontage should be complete and we will finally see the finished product. Good job everyone!

RiverView Condos Construction Update
February 26 - March 2 a busy week as Larry (Master Plasters) and his crew continue to work on dry walling Units #8 & #7. The JB Boys (and Scott) have finished up dry walling in Unit #6 and the warm weather allowed for the stone to go on units #6, 7 & 8. Looking great! Our shingling crew (Brandon Poole) managed get a great start on the east side of the garage before the snow arrived. The siding also got starting as on the garage. Great thanks to John and his staff at Va